PROJECT NAME : Shophing Mall Dancing Fountain
PROJECT LOCATION : Densky Mir, Ashgabat, TURKMENISTAN
PROJECT OWNER : Renaissance Türkmen
PROJECT SCOEP : Turnkey construction of dancing fountain pool
PROJECT START DATE : 17.07.2011
COMPLETION DATE : 30.07.2011
PROJECT DURATION : 13 Days
PROJECT DETAILS :
• Fountain Pump: 54 Pieces
• Lighting: 125 pcs Power LED RGB DMX
• Automation & Software:
- Windows-based automation computer and LCD display control
- Dance music automation software program
- Analog / Digital PLC Group
- Driver group
- RGB DMX control, dimming and relay groups
- Ethernet connection for remote access
- 5 basic dance choreography
- Instant and daily choreography
• Mechanical & Electrical Hardware: Sand filtration system, automatic water level control system, automatic chemical dosing system