PROJECT NAME : Villa Infinty Swimming Pools
PROJECT LOCATION : Sapanca / Sakarya
PROJECT OWNER : Ali MS ALBALHAN
PROJECT SCOPE : Swimming Pool, Filtration Systems and Lighting Systems
and Pool Covering
PROJECT START DATE : 15.08.2019
PROJECT COMPLETION DATE : 14.10.2019
PROJECT TIME : 60 days
PROJECT DETAIL :
VILLA INFINTY SWIMMING POOL 1
Long edge infinite flooded swimming pool measuring 7.95 x 4 m, 1.8 m deep, 31.8 m2 area and 57.24 m3 volume
- Pre-filter pool circulation pump
- Polyester sand filter
- Automatic chemical dosing system
- Wall halogen lighting system
VILLA INFINTY SWIMMING POOL 2
Short edge infinite flooded swimming pool measuring 7.95 x 4 m, 1.8 m deep, 31.8 m2 area and 57.24 m3 volume
- Pre-filter pool circulation pump
- Polyester sand filter
- Automatic chemical dosing system
- Wall halogen lighting system