PROJECT NAME : Villa Swimming Pool
PROJECT LOCATION : Malatya
PROJECT OWNER : Baykan Textile Company
SCOPE OF THE PROJECT : Garden Infinity Swimming Pool
PROJECT INITIAL DATE : 01.03.2020
PROJECT COMPLETION DATE: 10.05.2020
PROJECT PERIOD : 69 days
PROJECT DETAILS :
VILLA GARDEN SWIMMING POOL, infinity overflow system
Swimming Pool: Overflow system swimming pool with a dimension of 6.00x12.00 m, a depth of 1.40 m, an area of 70 m2 and a water volume of 100 m3.
- Pool plaster&screed and insulation works
- 2.5x2.5cm glass mosaic coating inside of the pool
- White marble coating around of the pool
- Pool filtration system
- Pool mechanical - electrical system installation
- Pool automatic chemical dosing unit
- 8W mini spot and 36 W maxi spot Power LED pool lighting